Klabin postpones the startup of the first stage of Puma II until the second 2 weeks of August
Aug, 05, 2021 Posted by Ruth HollardWeek 202131
Klabin announced this Thursday that the scheduled date to begin the first stage of the Puma II Project has been changed to the second half of August.
Previously, this move was planned for the second half of July.
“This change is due to specific contingencies in the commissioning processes and pre-operational tests, and does not change the total investment foreseen for the project”, he explained in a relevant fact to the Securities Commission (CVM).
The Puma II Project, approved in 2019, will expand the capacity in the packaging paper segment through the construction of two paper machines with integrated pulp production at the Puma industrial unit in Ortigueira (PR).
Source: Money Times
To read the full original article, visit the link:
-
Ports and Terminals
Mar, 15, 2023
0
Porto Alegre sees 8.17% cargo throughput growth in early 2023
-
Ports and Terminals
Feb, 06, 2020
0
Antonina Port ranked fifth for growth amongst all Brazilian ports
-
Ports and Terminals
May, 12, 2022
0
Businesspeople want to create a maritime trade lane between Brazil and Cape Verde
-
Grains
Jun, 14, 2023
0
Brazil farmers harvest 2.2% of 2023 second corn crop, AgRural says